Electrical systems inside data centers are slowing plans to expand AI computing, a Fluke Corporation-commissioned survey released Tuesday found across six countries, including the United States.
Fluke said 78% of operators reported a power-system problem in the preceding year with consequences ranging from a serious near-miss or a delay to disruption or downtime. The figure includes more than outages and should not be read as an outage rate. Only 33% said their electrical infrastructure was fully ready for denser AI workloads.
The pressure extends beyond equipment inside facilities. In the survey, 76% said access to sufficient power and grid capacity placed a moderate or severe limit on expansion. Respondents reported an average 12-month wait for an additional grid connection or more power capacity for AI and graphics processing unit (GPU) expansion.
Power-quality problems had limited the ability to deploy or run dense AI or GPU systems for 29% of operators, Fluke said. Electrical skills shortages had delayed upgrades or new capacity for 34%, while 60% said recruiting qualified electrical technicians had become harder.
The findings also point to gaps in detecting faults early. Fewer than half of respondents, 45%, said they could monitor critical electrical systems in real time. Another 29% said an electrical problem was identified only after equipment failed, performance suffered or downtime occurred.
A separate Uptime Institute survey found that 53% of operators had difficulty finding qualified job candidates in 2026, up from 46% in 2025. Uptime linked hiring pressure to industry growth, retirements and an insufficient pipeline of new workers.
Uptime also reported that the average of facilities’ typical server-rack power densities exceeded 11 kilowatts per rack, compared with 9 a year earlier. A small number of facilities with typical racks above 30 kilowatts helped lift that average. Excluding them, the average was 7.8 kilowatts per rack, up from 7.5.
Fluke said its survey covered 1,300 data center operators and industry professionals across six countries. Fluke sells electrical testing and monitoring equipment. Fluke Corporation President Parker Burke described electrical infrastructure inside data centers as “a critical bottleneck.”