MDU Resources Group, Inc. plans $3.488 billion for utility and pipeline investment from 2027 through 2031, raising its current capital outlook for U.S. energy networks by about 12%.
The company announced the plan Nov. 16. Annual spending is projected at $618 million in 2027, $668 million in 2028, $695 million in 2029, $906 million in 2030 and $601 million in 2031. Electric utility projects account for $1.522 billion, natural gas distribution for $1.345 billion and pipeline work for $621 million. MDU says the total is about 22% above its capital investment in 2022–26.
The electric allocation spans grid upgrades, substation work, transmission expansion and generation, including the Jamestown-to-Ellendale line. MDU says gas distribution funds will help update and extend its network. Pipeline projects include the Line Section 32 Expansion Project and Minot Industrial Expansion Project.
The plan does not include the proposed Bakken East Pipeline Project, which MDU estimates would require another $2.8 billion to $3.1 billion. The approximately 350-mile project would carry natural gas from western North Dakota’s Bakken region toward Fargo, with initial capacity of 1.4 billion cubic feet per day. MDU’s board advanced the project with a final investment decision on Sept. 30.
MDU is weighing financing arrangements that could involve financial or strategic investors. The company expects WBI Energy to retain majority ownership and operational control. Construction is expected during the 2028–30 seasons, with service planned in phases for late 2029 and late 2030; regulatory approval is still required.
MDU’s near-term funding outlook includes $70 million in planned equity issuance for 2027 and $100 million for 2028, excluding Bakken East. It expects internally generated cash and debt to cover the remaining capital needs, and plans to reassess equity needs beyond 2028.
The comparison uses MDU’s $3.1 billion forecast for 2026–30, which the company described as current in May 2026. MDU announced a $3.4 billion plan for 2026–30 in November 2025, but its May 2026 release gave no reason for the subsequent $3.1 billion forecast. MDU anticipated filing a Section 7(c) application with the Federal Energy Regulatory Commission (FERC) in the fourth quarter of 2026 for Bakken East.