North Carolina Approves Duke Rate Hikes, Revises Data Center Tariff

Duke projects higher monthly household bills in 2027. The new rates are expected to take effect Jan. 1, 2027.

Updated 2 min read
Pedestrians pass the North Carolina Utilities Commission offices in Raleigh. / EconoTimes.ai
Pedestrians pass the North Carolina Utilities Commission offices in Raleigh. / EconoTimes.ai

The North Carolina Utilities Commission approved higher Duke Energy electricity rates and revised terms for large data centers, putting household bills and the allocation of future grid costs in focus.

The Nov. 16 orders set a two-year average annual rate increase of 3.7% for Duke Energy Carolinas, compared with 3.4% for Duke Energy Progress. Duke projects respective revenue increases of $496 million and $338 million, pending final calculations with the Public Staff of the North Carolina Utilities Commission.

For Duke Energy Carolinas households using 1,000 kilowatt-hours a month, Duke estimates a $6.53 monthly bill increase in 2027 and a further $4.66 in 2028. Duke Energy Progress projects increases of $9.62 and $5.89 in those years, respectively. The bill amounts are estimates.

The approved schedule for data centers with demand above 50 megawatts retains some existing requirements and adds others. Facilities with demand above 100 megawatts must sign contracts of at least 15 years. Minimum billing demand is set at 75% of contracted demand, tying that portion of the charges to reserved capacity even when a facility uses less electricity.

Data-center customers must contribute to facilities built specifically for their service and provide letters of credit for transmission upgrades. They must also provide security for a stranded-generation charge, with a possible payment when a contract ends. The commission has yet to determine how some transmission costs will be assigned and how that generation charge will be calculated. Duke said it is assessing those parts of the orders.

Duke says the terms are intended to protect existing customers from costs associated with large new power users. The Southern Environmental Law Center, representing four advocacy groups, partially supported the data-center tariff but opposed the orders overall. The groups said questions remain about who will pay for grid and power-plant costs.

The commission authorized a 9.8% return on equity for both utilities and provided for customer refunds if planned infrastructure work is delayed. Each utility committed $10 million in shareholder funds for customer assistance.

Duke said Nov. 5 that signed agreements covered 7.8 gigawatts of its 15.4-gigawatt late-stage large-load pipeline, which includes manufacturing projects as well as data centers.

Duke expects the new rates to take effect Jan. 1, 2027, when the two utilities plan to merge while initially retaining separate rates.