Two national approvals stand between a proposed Panvel-Vasai suburban line and tendering, following a reported Railway Board committee decision, The Times of India reported, as cited by NDTV Profit.
NDTV Profit's Nov. 17 report named the panel the Project Evaluation Committee. A Nov. 13 report by Prime Time 24 called it the Project Appraisal Committee. Both accounts said the proposal received committee backing. They reported that NITI Aayog and India's Union Finance Ministry must approve the project before railway officials can seek bids.
The Maharashtra Cabinet approved the broader Mumbai Urban Transport Project Phase 3B in September 2025, according to a state government statement cited by The Indian Express. The package spans 136.652 kilometers and totals Rs 14,907.47 crore. It includes a 69.226-kilometer New Panvel-Vasai stretch, while the package cost covers other works as well.
Reports describe the proposed corridor as about 69.23 kilometers long, with 17 stations and roughly 28 kilometers of elevated track. The line is intended to give suburban passengers a direct connection between Panvel and Vasai. Some current trips can require transfers elsewhere on Mumbai's network, including at Kurla or Dadar, NDTV Profit and Prime Time 24 reported.
Published estimates for the corridor's standalone cost differ. NDTV Profit put it at Rs 2,711 crore, while Mid-Day reported a revised completion estimate of Rs 12,710.82 crore in September 2025. The reports do not explain the difference; the Rs 14,907.47-crore figure applies to the wider package.
A 2013 draft feasibility report from Mumbai Railway Vikas Corporation examined an earlier Panvel-to-Virar route along the Panvel-Diva-Vasai line, but it does not establish the current design. The reported next step is approval from NITI Aayog and the Finance Ministry; the accounts give no date for those decisions or for tendering.