DENVER, Jan. 16, 2018 -- When the structural revitalization of Kansas State University’s Memorial Stadium began in November of 2013, engineers and builders turned to a unique construction material to solve some complex engineering challenges. The renovations have transformed the stadium’s wing buildings into a fully modern black box theater on one side and a new student services center on the other. After deciding to reuse the majority of the stadium’s concrete riser seating as green roofs for the buildings below, a lightweight material was needed. The solution, Foam-Control® EPS Geofoam from ACH Foam Technologies.
|
|||||
“Initially, the thinking was to patch the concrete and then cover the stands with a layer of soil to develop the desired contours of the green roofs,” shares Sean Zaudke, Vice President with Gould Evans, designers for the west stadium’s transformation. “However, when the structural loading report came back it was clear we couldn’t add a tremendous amount of weight to the roofs and still comply with today’s building code requirements.”
Made from engineered expanded polystyrene (EPS), at approximately one-percent of the weight of traditional earth materials, Foam-Control Geofoam provided a lightweight way to fill in the space between each row of seating. Foam-Control Geofoam also has a tremendous R-Value that remains constant over the product’s entire life cycle and doesn’t absorb infiltrating water - both of which make it a great roof insulation. On the construction side, the biggest challenge was the stadium’s concrete risers that had been poured nearly a hundred years earlier. Built using an antiquated construction methodology, weather and the passage of time had taken a toll, resulting in no two steps being exactly alike.
“Figuring out the contours of all the steps was really quite a puzzle,” says Curtis Calvert, project manager for Hutton Construction. Calvert credits the roofing subcontractor for precisely determining the most efficient way to cover the slope without much material or labor waste. “During preconstruction, the installer came out and mapped every inch of the stadium, which allowed each piece of Geofoam to be cut and configured to a specific placement on the slope.”
Today, construction is complete, and the stadium’s vegetation has rooted. In the fall of 2016, new students experienced the centralized services of the Berney Family Welcome Center for the first time and the revitalized Purple Masque Theater on the other side has also thrived.
Contact Information:
Mary Burk - [email protected] / 303.645.4114
Sean O’Keefe - [email protected] / 303.668.0717
A photo accompanying this announcement is available at http://www.globenewswire.com/NewsRoom/AttachmentNg/5583ec97-11f8-469a-91be-5af9fd23100c


Instagram Outage Disrupts Thousands of U.S. Users
Missouri Judge Dismisses Lawsuit Challenging Starbucks’ Diversity and Inclusion Policies
Once Upon a Farm Raises Nearly $198 Million in IPO, Valued at Over $724 Million
Nvidia CEO Jensen Huang Says AI Investment Boom Is Just Beginning as NVDA Shares Surge
SoftBank Shares Slide After Arm Earnings Miss Fuels Tech Stock Sell-Off
TSMC Eyes 3nm Chip Production in Japan with $17 Billion Kumamoto Investment
FDA Targets Hims & Hers Over $49 Weight-Loss Pill, Raising Legal and Safety Concerns
TrumpRx Website Launches to Offer Discounted Prescription Drugs for Cash-Paying Americans
SpaceX Pushes for Early Stock Index Inclusion Ahead of Potential Record-Breaking IPO
Amazon Stock Rebounds After Earnings as $200B Capex Plan Sparks AI Spending Debate
Baidu Approves $5 Billion Share Buyback and Plans First-Ever Dividend in 2026
Nasdaq Proposes Fast-Track Rule to Accelerate Index Inclusion for Major New Listings
Tencent Shares Slide After WeChat Restricts YuanBao AI Promotional Links
Weight-Loss Drug Ads Take Over the Super Bowl as Pharma Embraces Direct-to-Consumer Marketing
Prudential Financial Reports Higher Q4 Profit on Strong Underwriting and Investment Gains
OpenAI Expands Enterprise AI Strategy With Major Hiring Push Ahead of New Business Offering 