Bangladesh Starts Trial Power Supply From Rooppur Nuclear Plant

The first test period is planned to last eight to 10 hours, with commercial-scale supply planned after a successful 10-month trial.

Updated 1 min read
Transmission lines run beside the Rooppur Nuclear Power Plant near Ishwardi, Bangladesh. / EconoTimes.ai
Transmission lines run beside the Rooppur Nuclear Power Plant near Ishwardi, Bangladesh. / EconoTimes.ai

Bangladesh’s Ministry of Science and Technology public relations officer Md. Abdullah Al Mamun said Nov. 17 that Rooppur began a trial 350-megawatt power transfer, bringing Bangladesh’s first nuclear unit onto its national grid.

The Bangladesh Atomic Energy Commission said the initial supply period was planned to last about eight to 10 hours, followed by a roughly 28-hour pause and another four to six hours of technical and operational checks. The commission said full-scale commercial supply is planned after a successful 10-month trial under an agreement with the Russian contractor. It identifies Russia as providing financial and technical assistance for the project.

The grid connection follows the reactor’s first criticality on Oct. 11, when it began a self-sustaining reaction at minimum power. At that time, power-level tests and two further regulatory approvals remained before connection, according to EconoTimes’ earlier report on the commissioning milestone. Rooppur is being built with two Russian-designed reactors with a combined gross capacity of 2,400 megawatts, that report said.