Technology / Business

Add as a preferred source on Google

FAA to Reassess Remote Equipment Work After U.S. Flight Halt

The agency is examining two sites and has disabled a function on more than 60 Juniper routers already installed.

Updated 2 min read
A technician works beside an equipment shelter at a communications site in El Dorado, Arkansas. / TokenPost.ai (macro)
A technician works beside an equipment shelter at a communications site in El Dorado, Arkansas. / TokenPost.ai (macro)

The Federal Aviation Administration said it will review the timing of equipment work at remote sites after network instability led it to halt U.S. departures nationwide, disrupting travelers and airline operations.

The FAA said a surge of connection attempts destabilized aging network equipment and led it to order a precautionary ground stop on Friday, Nov. 13. The agency reported instability in communications and radar feeds. Separately, it said the disruption affected 17 of its 22 Air Route Traffic Control Centers. Some feeds remained available, and the FAA said aircraft already in the air landed safely. The FAA said air traffic resumed by 8:15 p.m. ET.

CBS News described the halt as only the second nationwide ground stop since the Sept. 11 attacks.

The FAA is examining a communications site in El Dorado, Arkansas, where L3Harris was installing a Juniper router, and a radar site in Amarillo, Texas, as possible sources of the data surge. The agency has not identified what triggered the instability.

In a CBS News video, senior transportation correspondent Kris Van Cleave questioned the choice to carry out equipment work on a Friday afternoon. The FAA said remote-site replacements have generally taken place during the day for decades. Major control facilities are typically maintained overnight, the agency said, and it will review the remote-site schedule.

The disruption affected passengers and airline operations. On Sunday, Nov. 15, Transportation Secretary Sean Duffy said aircraft and crews were out of position and recovery might take until Monday, as EconoTimes previously reported. Air Canada estimated about 250 cancellations on Friday, Nov. 13, affected about 27,000 passengers.

The administration has requested $50.1 billion for aviation infrastructure, including $10.1 billion for air traffic control technology, as EconoTimes previously reported on the funding push. The Transportation Department has described the work as a shift from aging copper lines to fiber. The FAA has paused Juniper router installations and disabled a relevant function on more than 60 routers already installed. The agency and L3Harris continue investigating; the FAA has not announced a date for findings or for its review of remote-site work timing.