Nomura has moved more of its expected Nvidia Rubin-family deliveries into 2027, citing production constraints and SpaceX’s planned computing buildout as demand for advanced systems expands.
Nomura’s new 2026 estimate for combined Rubin and Rubin Ultra units is 1.63 million, 19% below its previous 2.02 million forecast. The firm’s 2027 NVL72 projection moved higher, to 75,000 from 66,000.
For 2026, Nomura put its NVL72 estimate at 60,000, down from 62,000. It attributed the shift to component bottlenecks and production delays that moved some late-2026 deliveries into early 2027. Even so, the updated two-year total is higher than under the previous forecast.
Nomura cited weak yields for high-bandwidth memory 4 (HBM4), constrained advanced-packaging capacity at TSMC and the greater cooling burden of denser Rubin systems. Rubin products target data-center workloads, where higher-performance machines depend on specialized memory, chip packaging and thermal management.
Nvidia’s fiscal third-quarter 2027 figures showed $115.8 billion in revenue, of which approximately $107.6 billion came from data-center operations. The company projected $130 billion in fiscal fourth-quarter 2027 revenue, while its fiscal 2028 growth view rose to roughly 75% from 70% previously.
Nomura tied the higher 2027 NVL72 view to SpaceX’s plan to lift computing capacity from about three gigawatts at 2026 year-end to above 13 gigawatts a year later. For 2027, the firm placed the possible combined share of Nvidia rack purchases going to SpaceX/xAI and neocloud providers at 55% to 60%.
Taken together, the revisions point to timing as the main change: supply limits affect when systems arrive, while large computing operators remain part of Nomura’s longer-term outlook.