A proposed A$32 billion data center campus in rural Queensland has drawn 595 objections or delay requests, highlighting local concerns over water, power and housing.
The project received 598 submissions: two supported it, one was neutral and 595 objected or requested a delay.
Zerra DC is proposing the project across 725 hectares of former farmland near Dalby, roughly 250 kilometers west of Brisbane. The four-building plan calls for 1.44 gigawatts of computing capacity, while electricity demand could potentially reach 2.16 gigawatts.
Anthropic, the company behind the Claude chatbot, is expected to be the main customer. Residents have cited water consumption, power costs, construction noise, traffic and pressure on local housing.
Queensland authorities are assessing the proposal's possible effects on water resources and the environment. The objections do not automatically halt construction, although they may weigh in the approval review.
Concern intensified after Anthropic was identified as the intended anchor tenant on Sept. 15. The local council ended its submission period Nov. 11, while state officials continue reviewing the proposal.