Network operator RETN says AI-infrastructure demand has lifted optical-networking prices about 50% since the start of 2026, while longer lead times are complicating network planning for operators.
A Nov. 9, 2026, white paper from RETN, titled “AI, Connected,” described the shift. It said AI data centers are competing with telecommunications companies and network operators for chips and other components.
RETN said the procurement cycle has widened: orders that once took about three months now generally take 12 to 15 months, while some purchases require 18 months or longer.
The paper says most AI-related connectivity requests to RETN—about 80% to 90%—seek private links, dark fiber or dedicated interconnections. That mix points to demand for dedicated network capacity as AI data-center projects expand.
For projects beyond established data-center hubs, RETN said carrier coordination now starts two to five years before operations begin, compared with one to two years previously. The longer runway reflects the need to bring power, land and fiber together at more remote sites.
The paper treats fiber supplies separately from equipment pricing, giving a possible 2026 average of 2.8 times to more than five times the 2025 level for global spot-market optical fiber. That range refers to a potential annual average, not one current market price.
RETN said shortages may last until at least 2028. The supply squeeze makes AI data-center development more difficult because those projects also need power, land and fiber.