AUKUS Submarine Sales Could Keep U.S. Fleet Smaller for Many Years

A Congressional Budget Office analysis says transferring three to five Virginia-class submarines to Australia could reduce U.S. attack-submarine capacity through much of 2033-2053.

Updated 2 min read
A Virginia-class attack submarine sits moored at Naval Submarine Base New London in Groton, Connecticut. / EconoTimes.ai (mono)
A Virginia-class attack submarine sits moored at Naval Submarine Base New London in Groton, Connecticut. / EconoTimes.ai (mono)

A Congressional Budget Office analysis says the planned transfer of nuclear-powered attack submarines to Australia could leave the U.S. Navy with fewer operational boats for many years, even if Washington later orders replacements.

The AUKUS Pillar One arrangement envisions the United States selling Australia three to five Virginia-class submarines. Two used boats are expected in 2032 and 2035, followed by a new submarine in 2038. Two more new boats could arrive in 2041 and 2044, although the final number, condition and timing remain subject to decisions by both governments.

In the three-submarine scenario, the Navy would lose 65 operational submarine-years and 28 deployments from 2032 through 2060, according to the CBO. A five-submarine transfer without replacements would reduce capacity by 102 submarine-years and 43 deployments over the same period.

“[T]he sale of SSNs to Australia could reduce the number of attack submarines available to the Navy,” the CBO said, using the term for nuclear-powered attack submarines.

Replacing five boats would require production to rise to 2.33 attack submarines a year. Even then, the fleet would remain below the Navy’s 2025 plan level for 20 years, from 2032 through 2052. The Navy’s 2025 shipbuilding plan does not specify when replacement submarines for the AUKUS transfers would be ordered.

The industrial base is currently producing about 1.2 attack submarines annually, although Congress has funded two per year. The gap between appropriation and delivery has widened from six years to nine years, while Virginia-class construction now takes about 10 to 11 years, compared with five to six years in the 2000s. Shipyards are also building Columbia-class ballistic-missile submarines.

Under the 2025 plan, the CBO projects at least 50 U.S. attack submarines from 2032 and 66 by 2054, before fully accounting for AUKUS transfers. Australian boats could partly offset the reduction because they would be based in the Western Pacific and might reach a conflict involving China faster.

That offset would depend on Canberra. “Australia would control its own submarines, and their participation in any particular conflict would not be guaranteed,” the CBO said.

Australia’s Deputy Prime Minister and Defence Minister Richard Marles made a similar point in 2023, saying the first Virginia-class submarine would be under the “complete control” of the Australian government. Australia also plans to build SSN-AUKUS submarines with the United Kingdom, with the first locally built vessel planned for the early 2040s.

The plan follows earlier coverage of Australia’s planned nuclear-powered submarine fleet.