Agnico Eagle’s Canadian Malartic complex could produce about 1 million ounces of gold annually by 2033, a potential expansion path that depends on Odyssey development, a possible second shaft and satellite projects, according to OR Royalties.
The royalty company outlined the projections in a Nov. 19 release after Agnico Eagle’s investor day a day earlier. The figures describe a possible future production profile, not current output or a final development commitment. Agnico Eagle operates Canadian Malartic and controls project decisions.
The projected annual total comprises about 550,000 ounces from Odyssey’s first shaft and ramp, 200,000 to 250,000 ounces from a possible second shaft, 120,000 to 150,000 ounces from the Marban satellite pit and 80,000 to 100,000 ounces from the Wasamac underground project. Marban and Wasamac are each targeted to begin production in 2033.
OR Royalties said Odyssey Shaft No. 1 was 73% complete and that production from the shaft is planned for June 2027. Studies for a potential second shaft are expected to finish in the second half of 2027, with a permit amendment planned for 2028. The proposed second shaft could support an operation handling 8,000 to 10,000 tonnes of ore daily.
Agnico Eagle’s third-quarter release also described a potential route for Canadian Malartic to approach 1 million ounces of annual production as early as 2033, based on evaluations of a second Odyssey shaft, Marban and Wasamac. That release did not give the detailed project-by-project output estimates cited by OR Royalties.
OR Royalties also cited targets for two other Agnico Eagle projects. Upper Beaver is projected to produce about 210,000 ounces of gold and 3,600 tonnes of copper annually, starting at a processing rate of 5,000 tonnes of ore per day. Agnico Eagle is assessing a possible increase to 8,000 tonnes per day. An updated technical evaluation is expected in the second quarter of 2027, permits are expected in early 2028, and production ramp-up is targeted for the first half of 2030, subject to key permits.
Hammond Reef, a proposed open-pit mine, is targeting first production in 2032. Preliminary plans project annual gold output of 250,000 to 300,000 ounces over a 13-year mine life. An updated technical evaluation is expected in the second quarter of 2027; remaining permits and project approval could follow in 2029.
OR Royalties says it holds royalties on Canadian Malartic, Marban and Upper Beaver, giving it exposure to production from parts of those projects. Its release says Barnat open-pit mining resumed in late September after remediation. Agnico Eagle had said a July 1 rock movement at Barnat was expected to reduce Canadian Malartic output; the company said the event was not expected to affect Odyssey’s development or production outlook.
The next stated milestones are updated technical evaluations for Upper Beaver and Hammond Reef in the second quarter of 2027, followed by expected completion of studies for the possible second Odyssey shaft, Marban and Wasamac in the second half of the year.