Datasection Inc. cut its consolidated net sales forecast for the fiscal year ending March 31, 2027, after an AI infrastructure order included in its outlook was terminated, sharply reducing expected earnings.
The revised forecast, disclosed in a Nov. 16 company filing, puts consolidated net sales at ¥17.286 billion, an 89.3% drop from ¥162.193 billion. The earlier outlook had included ¥79.864 billion from an additional AI infrastructure order. Datasection now expects to recognize only a ¥5.578 billion project-structuring and referral fee.
The change turns expected profit attributable to owners of the parent from ¥8.704 billion into a ¥1.479 billion loss. Operating profit is forecast at ¥4.923 billion, down 80.2%, while adjusted EBITDA is projected at ¥10.202 billion, down 82.5%.
The filing does not name the customer or mention Tencent. Datasection said the revision reflects the terminated order, delays in project progress, slower development of prospective projects and prolonged negotiations over server specifications.
Datasection left sales from three AI data-center projects—one domestic and two overseas—out of the revised outlook after their expected operating schedules slipped. The new plan still includes ¥10.225 billion from one overseas facility already in operation. Revenue from the other projects was excluded because recognition during the fiscal year was not considered highly probable.
At one overseas project, prolonged talks with the customer over revised terms, including the move from NVIDIA B200-equipped servers to B300-equipped servers, pushed back operations. The property owner notified Datasection on Aug. 31 that it intended to terminate the facility-use agreement.
Datasection and its subsidiary, Datasection Australia Pty. Ltd., resolved to accept the termination on Nov. 16 and recorded a ¥2.751 billion loss on lease cancellation and a ¥314 million provision for loss on contract cancellation.
Datasection said it will continue commercializing the excluded projects and disclose another forecast revision if project progress or other factors require one. No specific date was scheduled for that update.