The U.S. Energy Department ordered PJM Interconnection to keep two Pennsylvania generating units available through Feb. 18, 2027. The department said the order addressed grid reliability needs in the mid-Atlantic.
The department issued the order on Nov. 20. It did so in an article titled “Energy Secretary Keeps Critical Generation Available in Mid-Atlantic.” The order directs PJM, working with Constellation Energy Corp., to keep Units 3 and 4 at the Eddystone Generating Station operating. It also directs PJM to use economic dispatch to limit costs.
The Eddystone units had been scheduled to shut down on May 31, 2025. The new order takes effect on Nov. 21, 2026. It remains in effect through Feb. 18, 2027. The order therefore keeps the two units available during the winter period identified by the department.
Energy Secretary Chris Wright said the administration was keeping the units available when demand was highest. He said the action was intended to reduce blackout risks and maintain affordable, reliable and secure electricity. “The energy sources that perform when you need them most are the most valuable,” Wright said.
Wright first ordered the units to remain online beyond their planned retirement in an emergency order issued May 30, 2025. That earlier order concerned the same two Eddystone Generating Station units. The department issued further orders later in 2025 and 2026, according to the statement.
The department said keeping the units operating had strengthened energy security in the PJM region. It said the units would remain available for households and businesses during the period covered by the order. The department identified grid reliability as the reason for continuing their availability.
PJM coordinates electricity transmission and wholesale power markets across parts of the eastern United States. Under the order, PJM is responsible for keeping the two Pennsylvania generating units available while working with Constellation Energy Corp. The order also calls for economic dispatch to limit costs while the units operate.
The department’s article described the action as keeping critical generation available in the mid-Atlantic. The order applies to Units 3 and 4 at the Eddystone Generating Station. Those units were originally scheduled to shut down on May 31, 2025, but the department’s emergency orders kept them online beyond that planned retirement date.
The latest order begins on Nov. 21, 2026, and ends on Feb. 18, 2027. During that time, the department said the units would support reliable electricity for households and businesses in the PJM region. Wright said the administration was acting when demand was highest to reduce the risk of blackouts.