Giga Energy has signed a 10-year lease worth about $1 billion for a 60-megawatt Texas data center, which the company says could create jobs and recurring local tax revenue.
Giga said Tuesday that the tenant is an unnamed U.S.-based AI cloud provider. The planned campus covers about 30 acres, and the company says it broke ground in July.
The project's name differs across Giga's Nov. 17 announcements. A release issued earlier that day called a 60-megawatt Hunt County campus under the same lease terms Project Marl. Giga's newsroom and a later release used Project Clay. The available announcements do not establish whether Marl and Clay are separate projects or whether one release used an incorrect name.
A June 23 record from the Texas Department of Licensing and Regulation (TDLR) lists BT Gateway Data Center at 4989 County Road 2656 in Royse City, Hunt County. It names Giga AFM LLC as the owner, gives the facility's size as 100,000 square feet and estimates its cost at $384 million. The tenant field says “Not Assigned.” The record does not identify BT Gateway as Project Clay or Project Marl, so it does not confirm whether the filing concerns the leased site.
Giga estimates that construction will employ about 300 people and that the operating facility will have 24 permanent full-time positions. It projects annual salaries of $116,000 to $180,000 and says the site could generate millions of dollars in recurring tax revenue, without specifying an amount.
The company says a closed-loop system will provide cooling without drawing on municipal or groundwater. It estimates that sinks and employee bathrooms would use an amount comparable to two homes' water consumption over a year. Giga says dedicated electrical infrastructure will let the campus use capacity it considers underused, leaving distribution capacity available to nearby homes and businesses. The company expects the campus to be ready for service in spring 2027.