Hewlett Packard Enterprise (HPE) expects shortages affecting memory components, including NAND flash, to continue through at least the second half of 2028, potentially prolonging pressure on customer order fulfillment.
HPE CEO Antonio Neri made the assessment during the company’s Monday earnings call. He said some lead times have extended beyond 40 weeks, while HPE also raised its fiscal 2027 outlook.
Micron Technology’s figures show the supply concern extends beyond HPE’s procurement needs. CEO Sanjay Mehrotra said about 75% of Micron’s 2027 production capacity had been sold. The company is discussing allocations for 2028, and some contracts extend into 2030 and 2031.
Micron’s fiscal fourth-quarter 2026 revenue reached a record $54.23 billion. The company has said supply and demand may be tighter in 2027 and 2028 than in the previous year.
Together, the comments show pressure on both sides of the purchasing cycle: HPE is reporting extended waits, while Micron says much of its near-term capacity is already committed. Micron’s long-term contracts also place future supply planning well beyond the next production year.
For HPE, the constraints could mean longer lead times, larger backlogs and higher component costs. HPE’s stock declined as much as 16% in a single day after the earnings release as supply concerns weighed on its backlog.
The immediate markers are HPE’s lead times above 40 weeks and Micron’s ongoing discussions over 2028 allocations.