NEW DELHI, Nov. 20, 2026 — India’s electric-vehicle charging expansion is encountering grid-connection hurdles as some electricity distribution companies seek large payments for high-capacity hookups, adviser Tarun Kapoor said.
“DISCOMs sometimes are not very cooperative,” Kapoor said at the Society of Indian Automobile Manufacturers’ first Growth and Readiness for EV Infrastructure Dialogue in New Delhi, according to Press Trust of India.
Kapoor said the “behind the metre” portion of charging-station costs can become expensive when a site needs 100 kilowatts or more. He proposed assigning a designated official at each distribution company to handle charging-station connection requests, PTI reported.
India’s Ministry of Power guidelines call for distribution companies to provide connections of up to 150 kilowatts to charging stations through expedited timelines and standard procedures.
Kapoor said electric vehicles could become one of the largest electricity-consumption sectors for distribution companies as India moves into a period of surplus power. He encouraged charging where vehicles remain parked during the day, including workplaces, offices, marketplaces and parking facilities, PTI reported.
Some public charging stations have utilization below 1%, making maintenance difficult for operators, Kapoor said, according to PTI reports.
The PM Electric Drive Revolution in Innovative Vehicle Enhancement scheme includes ₹2,000 crore for public electric-vehicle charging infrastructure, battery-swapping stations and battery-charging stations. The Ministry of Heavy Industries puts the program’s total outlay at ₹10,900 crore.
The Press Information Bureau said the scheme could support about 72,000 public charging stations. Kapoor said the government would be willing to provide more funding if needed.
The charging dialogue was held Nov. 20 at ITC Maurya in New Delhi, according to the Society of Indian Automobile Manufacturers’ event listing.