Nvidia had made no payments under guarantees by Oct. 25, though its potential obligations could total $118 billion as data center projects linked to OpenAI advance.
The ceiling covers guarantees to Nvidia partners. Up to $105 billion is tied to construction associated with OpenAI. The potential support would take effect gradually as projects are built, making the $118 billion a maximum exposure rather than an amount already paid or a current debt balance.
In earlier coverage of Nvidia’s guarantee commitments, EconoTimes reported potential gross exposure of $108.5 billion. That figure included a guarantee capped at $105 billion for SB Energy leases on an Ohio campus intended to support OpenAI’s initial 4.25 gigawatts of IT capacity, plus $3.5 billion tied to selected AI cloud partners’ land, power and building-shell commitments.