Oracle Corp. is transporting natural gas by truck to several data centers across the United States as delays in pipeline construction threaten the company's artificial intelligence infrastructure expansion plans, Bloomberg reported Thursday.
The technology giant is using temporary natural gas deliveries to keep its data center projects on schedule while waiting for permanent pipeline connections. The strategy highlights the growing energy challenges facing companies investing heavily in AI computing infrastructure.
According to the report, Oracle relied on truck-delivered natural gas for more than a year to power a data center near Salt Lake City, Utah, while pipeline construction and integration remained incomplete.
The company has adopted a similar approach at a major data center campus under development for OpenAI in Shackelford County, Texas.
Oracle is also evaluating the use of trucked natural gas in New Mexico, where pipeline delays could disrupt the development of Project Jupiter, another large-scale data center facility. Temporary gas supplies would allow initial operations to begin before permanent infrastructure becomes available.
Last month, Oracle issued a force majeure notice to the New Mexico project's developer, potentially shielding the company from certain financial obligations if construction delays continue.
The pipeline challenges intensified after New Mexico regulators rejected a proposed route from Energy Transfer LP, forcing the company to redesign its infrastructure plans. Consequently, the pipeline's expected operational date shifted from this summer to next year.
Energy providers are increasingly offering alternative solutions to address electricity shortages affecting AI data center construction.
Superior Plus Corp.'s Certarus and VoltaGrid LLC are among the companies supplying compressed natural gas transportation services to support facilities awaiting permanent energy infrastructure.
Oracle previously partnered with Certarus for its Utah operations and selected VoltaGrid to support its Texas data center development.
In a social media statement, Oracle praised VoltaGrid for providing affordable energy solutions that help maintain the planned availability of Oracle Cloud Infrastructure capacity for customers.
The company's aggressive investment in AI data centers has placed additional pressure on its finances. Oracle currently reports negative free cash flow, a situation expected to persist until more facilities become operational.
The reliance on temporary natural gas supplies underscores the growing importance of reliable energy access as Oracle expands its cloud computing capacity to meet rising artificial intelligence demand.


Amazon Cuts More Jobs as AI Investment Expands
Rapidus Seeks Chip Customers as Japan Pushes 2nm Semiconductor Revival
Anthropic Expands Claude Access for Cyber Defense Teams
EU Gives Crypto Platforms Three Months to Remove USDT Under MiCA Rules
Zcash Prepares for NU7 Upgrade as Zebra Gets Key Security Fixes
US Suspends Microsoft, Adobe From Green Card Program
Zcash Privacy Demand Rises as AI Exposes Bitcoin Transactions
SpaceX Seeks $40 Billion for Nvidia AI Chips
DogecoinVM Makes DOGE Transactions 300x Faster
Apple Names Steve Smith M&A Chief in Leadership Shakeup
OpenAI, Anthropic Back Mandatory AI Breach Reporting in Australia
TSMC Q3 Revenue Beats Estimates as AI Chip Demand Surges
Florida Seeks Tougher Meta Rules to Protect Young Users
LG Electronics Shares Slide as Q3 Profit Misses Estimates
TikTok Accused of Testing Fake Safety Tools on Users
Europol Warns Bitcoin Wallets Face Quantum Computing Risk
Tencent Shares Fall as $5 Billion AI Bond Sale Weighed 