Business / Economy

Add as a preferred source on Google

Singapore, Batam Yards Build €6 Billion Platforms for North Sea Wind

Seatrium and GE Vernova are delivering three 2-gigawatt offshore converter platforms for Dutch grid operator TenneT as Europe expands North Sea transmission links.

Updated 2 min read
Workers assemble an offshore converter platform topside at Seatrium's Tuas shipyard in Singapore. / EconoTimes.ai
Workers assemble an offshore converter platform topside at Seatrium's Tuas shipyard in Singapore. / EconoTimes.ai

Seatrium is constructing three offshore converter platforms in Singapore and Batam for Dutch transmission operator TenneT, supporting the delivery of North Sea wind power to Europe’s mainland grids.

A Seatrium and GE Vernova consortium secured the three contracts, worth about €6 billion in total, in March 2023. The projects are IJmuiden Ver Beta, IJmuiden Ver Gamma and Nederwiek 2.

The two IJmuiden Ver units are planned roughly 62 kilometers from the Dutch coast, while Nederwiek 2 is expected about 95 kilometers offshore. Each 2-gigawatt platform will gather wind-generated electricity, convert it for high-voltage direct-current transmission through subsea cables and return it to alternating current onshore for the grid.

The contract specifications call for a 25,500-tonne topside and a 9,500-tonne jacket foundation for each platform.

Seatrium said fabrication was scheduled to start in stages from the third quarter of 2024 at its Singapore and Batam facilities. Its 2024 annual report recorded the first steel cut for IJmuiden Ver Beta and said construction was under way on all three platforms.

“The Offshore Converter Platforms will be progressively installed to serve TenneT’s three offshore wind farm projects,” Seatrium said in its March 2023 announcement.

Mammoet said TenneT’s broader 2-gigawatt program includes 15 offshore high-voltage direct-current connections, with eight planned in the Netherlands and seven in Germany. Installations are scheduled through 2032 as the network reaches wind farms farther from shore.

WindEurope says wind supplies about 20% of Europe’s electricity demand and could account for 30% by 2030 under its scenario. GE Vernova is providing the converter technology, while Seatrium is building and installing the offshore structures.

Related articles