Business

Add as a preferred source on Google

Hindustan Zinc Approves ₹800 Billion Plan to Expand Metal Capacity

The target spans zinc, lead, ore and silver capacity, but the company did not forecast actual output.

Updated 2 min read
Zinc smelting towers stand at Hindustan Zinc’s Debari complex near Udaipur, Rajasthan. / EconoTimes.ai
Zinc smelting towers stand at Hindustan Zinc’s Debari complex near Udaipur, Rajasthan. / EconoTimes.ai

Hindustan Zinc Limited approved an estimated ₹80,000 crore (₹800 billion) plan Nov. 16 to lift annual metal capacity to 2 million tonnes, citing expected zinc demand growth tied to steel and infrastructure. The target sets a capacity goal, not a forecast of actual output, so the filing does not establish how much additional metal will reach global markets.

The company's exchange filing says existing metal capacity was about 92% utilized in fiscal 2025-26. Hindustan Zinc plans to fund the expansion through internal accruals and debt, but did not disclose how much would come from either source.

The investor presentation outlines new smelting capacity of 500,000 tonnes of zinc and 200,000 tonnes of lead per year, expected to be commissioned within three to five years. The company's target breakdown is 1.6 million tonnes of annual zinc capacity and 400,000 tonnes of lead capacity.

At Debari in Rajasthan, Hindustan Zinc increased the planned capacity of a previously approved integrated zinc smelter from 250,000 to 265,000 tonnes a year within the same budget. The presentation expects the project to be commissioned by the second quarter of FY2029.

The plan also targets annual ore production capacity of 35 million tonnes, up from 19.3 million. Hindustan Zinc says the estimate is based on a conceptual plan and may change as the details are developed. Silver refining capacity is targeted to rise to 1,500 tonnes a year from 800 tonnes, including 700 tonnes of new annual capacity from a planned refinery.

Hindustan Zinc's presentation projects India's crude steel capacity will grow from 205 million tonnes in FY2025 to 300 million in FY2030. It also says domestic zinc demand could double over the next five to 10 years; both are company projections. The next stated project milestone is the expected commissioning of the Debari smelter by the second quarter of FY2029.

Related articles