Meta is reassessing the timeline and interim milestones for its value-chain net-zero goal as demand for artificial-intelligence infrastructure accelerates and energy-system constraints persist.
Meta reported 2025 net emissions of 11.8 million metric tonnes of carbon dioxide equivalent, a 45% increase from the previous year. The company said the rise came mainly from Scope 3 emissions tied to purchased goods and services and capital goods.
Electricity consumption climbed 35% to 24,849,122 megawatt-hours in 2025 from 18,423,634 MWh a year earlier as additional data centers came online. Meta said interconnection queues, permitting, transmission construction and low-carbon supply chains have not kept pace with infrastructure demand.
“Demand for AI infrastructure has grown faster than almost anyone projected, arriving on a timeline measured in quarters rather than decades, and meeting it has meant building at a pace and scale the industry has never attempted,” Rachel Peterson, Meta vice president of data centers, and Blair Swedeen, Meta global head of net zero and sustainability, wrote. They said meeting that demand required building at a pace and scale the industry has never attempted.
Meta said its ambition remains net-zero emissions across its value chain in 2030, but it is reviewing that timeframe and its near-term intensity targets. Peterson and Swedeen wrote that the company is “re-evaluating our timelines, sequencing, and interim milestones.”
Anadolu Agency reported that Meta has not announced a replacement deadline and plans to publish the outcome of the review.
Meta said it matched 100% of its annual electricity use with clean and renewable energy in 2025, extending that record to six consecutive years. It contracted more than 10 gigawatts of additional capacity during the year, bringing total contracted capacity above 30 GW across seven countries and 28 U.S. states.
Suppliers representing 62% of Meta’s emissions had science-aligned reduction targets by the end of 2025, compared with 48% a year earlier. Meta also reported removing 80,000 metric tonnes of carbon dioxide equivalent through carbon-removal projects addressing residual Scope 1 and Scope 2 emissions.
Al Jazeera, citing the International Energy Agency, reported that data centers worldwide consumed about 415 terawatt-hours of electricity in 2024, roughly 1.5% of global electricity supply. The report said demand could nearly double by 2030. Meta has not specified which interim milestones will change; its next stated step is to publish the review’s outcome.