enCore Energy Says Texas Approved Its First Upper Spring Creek Wellfield

The company forecasts uranium extraction will begin in the first week of December 2026, after final inspections. A separate approval for a saline-water disposal well remains outstanding.

Updated 1 min read
Wellheads and utility pipes mark the Upper Spring Creek uranium project site in South Texas (AI-generated image / EconoTimes)
Wellheads and utility pipes mark the Upper Spring Creek uranium project site in South Texas (AI-generated image / EconoTimes)

enCore Energy said Texas regulators have approved the first wellfield at its Upper Spring Creek uranium project, clearing a step toward production at the South Texas site while a separate wastewater-well approval remains pending.

The company forecasts that oxygenated-water injection and uranium extraction will begin in the first week of December 2026, after final inspections. The authorization, Production Area Authorization 1 (PAA-1), covers the first production area at the company’s wholly owned project.

The Texas Commission on Environmental Quality (TCEQ) must separately approve Waste Disposal Well WDW-467. enCore said the well, intended to handle saline water from operations, has been built and that approval is expected in December 2026. The company does not expect the wellfield to reach its designed operating rates before that approval.

The project uses in-situ recovery, which brings uranium to the surface after a solution mobilizes it underground. EnCore plans to send uranium-loaded resin from the site’s ion-exchange plant to its Rosita Central Processing Plant, where it will be processed into yellowcake.

TCEQ’s permit materials describe PAA-1 as covering Class III underground injection wells for uranium recovery and groundwater restoration. The agency’s online draft permit does not include a completed issuance date.